Key takeaways
- A change of use, a first tenant in a new space, changes to ventilation or equipment, or a change in occupant load can each trigger a building permit.
- Planning approval must be in place before the building permit is issued, so the two processes should be started together.
- The City of Calgary's guidance cites about 21 calendar days for a minor tenant improvement and 56 for larger projects, counted from a complete application.
A lease is signed, an opening date is set, and the question arrives: do we need a permit for this? For commercial tenant improvements in Calgary, the answer depends on what the work changes about the space, not on how large the budget is.
What triggers a building permit
The City of Calgary's guidance for commercial alterations identifies several common triggers. A building permit is generally required when:
- the space is being put to a new use, for example an office becoming a clinic or a retail unit becoming a restaurant;
- the tenant is the first occupant of a new shell space;
- the work changes ventilation or mechanical equipment;
- the work changes the occupant load, such as adding seating or assembly space.
Purely cosmetic work, such as painting, flooring or replacing millwork like for like, usually does not need a building permit. Trade permits for electrical, plumbing, gas or HVAC work are separate and may still apply.
Planning approval comes first
A building permit confirms that the construction meets the building code. A development permit, or other planning approval, confirms that the use is allowed at that location. The City states that planning approval must be in place before a building permit is issued.
In practice this means checking the land use for the address before the lease is signed, and starting any change-of-use application at the same time as the drawings, not after them.
How long review takes
The City's published guidance cites about 21 calendar days for a minor tenant improvement and about 56 calendar days for larger projects. Both figures assume a complete application. Incomplete drawings, missing professional schedules or an unresolved planning approval stop the clock.
Those durations cover review only. A realistic schedule from lease signing to opening also allows for design, pricing, long-lead items such as millwork and mechanical equipment, construction and inspections.
Which code applies
Commercial work in Alberta is designed to the National Building Code, 2023 Alberta Edition, and the National Energy Code of Canada for Buildings 2020. Renovations are assessed on the work being done; the designer and the City confirm how far upgrades to existing conditions are required.
Five ways to avoid losing weeks
- Confirm the permitted use before signing the lease. A use that needs planning approval adds time.
- Review existing conditions early. Base-building mechanical capacity, washroom counts and exiting often decide the scope.
- Submit complete drawings. Missing information can delay review and require another submission.
- Order long-lead items while the permit is in review, where the lease and the risk allow.
- Involve the contractor before pricing. Early scope review catches interface problems with base-building systems.
Requirements change, and each address is different. Confirm the requirements for your project with the City of Calgary and your design professionals before relying on any timeline.
Sources
This article is general information, current as of the date shown. It is not legal, financial, engineering or code-compliance advice. Confirm requirements for your project with qualified professionals and the authority having jurisdiction.