Key takeaways
- The delivery model decides who carries design risk, when the price is known and how much the owner must manage.
- Stipulated price suits complete designs; construction management suits early starts and evolving designs; design-build suits owners who want one accountable party.
- Canada has standard CCDC contract forms for each model, which shortens negotiation and makes risk allocation familiar to all parties.
Before an owner chooses a builder, there is an earlier choice that shapes the whole project: the delivery model. It determines who is responsible for the design, when the price becomes firm, and how many organizations the owner has to manage. Three widely used approaches are outlined below.
Stipulated price (design-bid-build)
The owner engages consultants to complete the design, then contractors price the finished documents and the owner signs a fixed-price contract with one of them.
Works well when the design is complete and unlikely to change, and the owner values a competitive price for a defined scope.
Watch for the gap between design and construction. Where the builder is engaged only at tender, constructability issues and cost differences can emerge after design decisions have been made. Separate preconstruction advice can help address this earlier. Changes after award are priced as change orders.
The standard Canadian form is CCDC 2, Stipulated Price Contract.
Construction management
The owner brings a construction manager onto the team during design. The manager advises on cost, schedule and constructability, then tenders the work to trades in packages. The owner sees trade pricing as it comes in.
Works well when the project must start before the design is complete, when the scope is likely to evolve, or when the owner wants cost advice while decisions can still change.
Watch for price certainty. The price basis depends on the contract. Under CCDC 5B, work starts on an actual-cost-plus-fee basis, with options for a guaranteed maximum price or conversion to a stipulated price by agreement.
There are two common forms. Under CCDC 5A, the construction manager provides services and the owner contracts directly with trades. Under CCDC 5B, the construction manager provides services and also holds the trade contracts.
Design-build
The owner signs one contract with a single entity responsible for both design and construction. The design-builder engages the architects and engineers.
Works well when the owner wants a single point of accountability, has a firm budget or occupancy date, and can describe requirements clearly at the outset.
Watch for the quality of the owner's statement of requirements. Because the design is developed by the builder's team, what the owner asks for at the start largely defines what is delivered.
The standard Canadian form is CCDC 14, Design-Build Stipulated Price Contract.
A side-by-side view
| Question | Stipulated price | Construction management | Design-build |
|---|---|---|---|
| Who holds design responsibility? | Owner, through its consultants | Owner, through its consultants | Design-builder |
| When is the price known? | At tender, after design | Progressively, as packages are tendered | At contract, against owner's requirements |
| Builder input during design | Limited unless engaged for preconstruction | During design | During design |
| Can construction overlap design? | Usually sequential | Can be phased | Can be phased |
| Owner's management effort | Moderate | Higher | Lower |
How to decide
Three questions usually settle it. How complete is the design today? How fixed is the completion date? And how much capacity does the owner have to manage consultants and decisions?
A complete design and a flexible date point to stipulated price. An incomplete design and a pressing date point to construction management. A firm budget, a firm date and a preference for one accountable party point to design-build.
Krangard Construction considers all three models for projects in Alberta and British Columbia. The contract model, scope and responsibilities are confirmed after reviewing the project information.
Sources
This article is general information, current as of the date shown. It is not legal, financial, engineering or code-compliance advice. Confirm requirements for your project with qualified professionals and the authority having jurisdiction.